SWDP Review Timetable Updated

The three South Worcestershire Councils have updated their Local Development Schemes (LDS). The latest versions were adopted at Council meetings held on 16 September 2020 (Wychavon District Council), 29 September 2020 (Malvern Hills District Council) and 30 September 2020 (Worcester City Council).  The LDS is a project management document which sets out the council priorities for producing planning policy documents over the coming three years.

The new timetable for the SWDP Review is as follows:

Additional Preferred Options (Regulation 18) Consultation – March-April 2021

Publication (Regulation 19) Consultation – November-December 2021

Submission (Regulation 22) – March 2022

Independent Examination (Regulation 24) – May 2022-January 2023

Receipt of Inspector’s Report (Regulation 25) – March 2023

Adoption (Regulation 26) – April 2023

Click here to see the Project Plan and Local Development Schemes for the three South Worcestershire Councils